CLIENT AND PROJECT:
Ameren Substation Oil Containment,
St. Louis, MO
PROJECT TYPE: CURRENT SITE IMPROVEMENTS
Ameren depended on the Interface’s quality and safety control measures to successfully install a new oil containment system in an active, energized substation.
Safety Management
The oil containment system was installed without any safety incidents or unscheduled electric outages.
Notable Installations by the Interface Construction Corporation Team
- Shoring for the containment system holding a 20,000-gallon oil tank within an energized Ameren substation
Interface self-performed the cast-in-place concrete and oil containment system while working outside the minimum approach distances from active, high-voltage electric lines, requiring an in-depth safety plan consisting of a full-time monitoring system.
Key Project Personnel
Mark Boehms-Interface Vice President and Project ManagerBob Lynch-Interface Superintendent
Ameren Design Team